Samples taken before a bedroom addition is tied into a 1950s tract house
Example project
- Home
- 1950s tract house in Norwalk with stucco walls, textured ceilings and a rear bedroom wall that will open into the addition
- Original request
- Build a bedroom addition off the back and cut a doorway through the old rear wall
- Testing
- A Cal/OSHA-certified asbestos consultant samples the stucco finish coat, the inside wall, the ceiling texture and the floor at the doorway
- Found
- Asbestos in the stucco finish coat
- Clear
- The inside wall, the ceiling texture and the floor
- Timeline
- Lab results first, then the removal is booked ahead of the framers
- Estimated testing cost
- $700
Scope of work
A visit by the consultant, a few samples, a lab result for each and a short report with the sample spots marked. Removing the stucco is priced on its own.
Project overview
In this example, a family in Norwalk is adding a bedroom behind their 1950s tract house. The rear wall gets a new doorway, and the stucco outside it will be cut back for the tie-in.
The rule skips the survey for a single-unit house when less than 100 square feet is removed, but the family wants to know the amount before the framers come. The stucco tests positive and the rest is clear, so the abatement crew is booked ahead of the framing.
The goal
The goal is a written answer before any wall is cut, so the framing starts on a plan that fits the old house.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the stucco, the wall, the ceiling and the floor.
- Results The report marks the stucco positive and the other three materials clear.
- Next The abatement crew is booked to cut back the stucco at the tie-in.
- Then The framers start on the new doorway.
Planning right
- Hold the framers until the lab results are in.
- Do not take samples yourself, the consultant knows what to cut.
- Mark the doorway spot on the rear wall for the consultant.
- Keep the report with the addition plans.